When a school authority in North Rhine-Westphalia reopened its refurbished two-court sports hall last autumn, the brief looked simple: replace everything from the basketball backstops to the mat trolleys. In practice it meant matching DIN 18032-3 impact requirements, RAL-matched powder coating, and a 22-week window that left no room for a second production run.
This is how the package was specified, built and shipped — and what we would quote differently next time.
The programme at a glance
| Standort | North Rhine-Westphalia, Deutschland |
| Einrichtung | Two-court school sports hall, 1,150 m² playing area |
| Scope | 6 wall-mounted backstops, 4 volleyball post sets, 90 gymnastics mats, 8 table tennis tables, 24 trolleys |
| Standards referenced | DIN 18032-3 (ball impact), EN 1270, EN 913, EN 14468-1 |
| Produktion führen Zeit | 26 days from approved drawings |
| Lieferung | 1 × 40HQ to Hamburg + 3 air-freight pallets for the opening event |
| On site | Remote installation supervision, printed 1:50 layout drawings |
Why German school halls are specified differently
Three requirements shaped almost every decision on this project, and they are the same three that come up in most German tenders we see.
Ball-impact Sicherheit kommt first
Under DIN 18032-3, a hall has to absorb a ball thrown at match speed without the wall fittings becoming a hazard. That is why wall-mounted backstops here are specified with folding arms that sit flat against the wall when not in use, and why every anchoring plate is calculated rather than picked from a catalogue.
Mats have to survive daily stacking
A 40 mm mat that loses its shape after one term is a false economy. We quoted 30 kg/m³ foam with a reinforced PVC cover and hook-and-loop edges, because the hall stores all 90 mats upright in trolleys twice a day.
Eins Lieferant, eins Zeichnung Satz
The authority did not want to coordinate a backstop vendor, a mat vendor and a table tennis vendor across three delivery windows. Consolidating the package into one container and one set of layout drawings was worth more to them than the last two percent of unit price.
The equipment package, item by item
| Artikel | Spezifikation | Qty |
|---|---|---|
| Wall-mounted basketball backstop | 1800 × 1050 mm acrylic board, 3.05 m rim height, folding arms, powder-coated frame | 6 |
| Volleyball Post Satz | 4-post system, net height adjustable 2.24–2.43 m, padded bases | 4 |
| Gymnastics mat | 2000 × 1000 × 40 mm, 30 kg/m³ foam, anti-slip PVC cover | 90 |
| Tisch tennis Tisch | 25 mm top, EN 14468-1, folding, four braked wheels | 8 |
| Ball and mat trolley | 150 kg load, 1.5 m depth to fit existing cupboards | 24 |
How the order actually ran
- Week 0 — Enquiry arrived with hall drawings, a photo of the existing wall build-up and the tender's equipment schedule.
- Week 1 — We returned a 1:50 layout proposal with backstop positions, mat storage plan and a 3D view of the playing end.
- Week 2 — Cover material swatches and RAL powder chips shipped by courier, not sent as screen mockups.
- Week 3 — Purchase order, 30% deposit, drawings signed off.
- Weeks 4–7 — Production, with a pre-shipment inspection and a photo/video report before packing.
- Week 8 — Container loaded, FCL to Hamburg.
- Week 12 — Arrival, customs clearance, delivery to site.
- Week 13 — Remote installation supervision over two video sessions; the school's own maintenance team hung the backstops.
Three details that took the longest
1. The wall, not the hoop. The playing-end wall was masonry, the side walls were stud partitions. One anchor schedule would have been wrong on half the hall. We asked for close-up photos of each wall and supplied two plate variants — a small change that avoided drill failures on site.
2. Mat Lagerung depth. The hall's existing cupboards were 1.8 m deep, but the doors only opened to 1.5 m. Standard trolleys would have jammed. We shortened the frame rather than asking the school to rebuild furniture that had just been installed.
3. RAL 5015 versus RAL 5017. Two blues that look identical on a monitor and obviously different on a 1,150 m² floor. Physical chips settled it in a day. For any colour-critical project, insist on a physical sample before production.
Packing and paperwork for EU buyers
Mats travelled rolled in woven bags with edge protection; frames were crated with corner blocks and steel strapping. All timber was ISPM-15 heat-treated and stamped. For the German consignee we supplied HS codes, packing lists by pallet, and material and test reports for the standards named in the tender on request. Nothing in the shipment needed re-packing at the port — which is the outcome that matters when a school opening date is fixed.
FAQ
What lead time should a German school plan for?
Eight to ten weeks door to door for a complete hall package, assuming drawings are approved before the summer break. Backstop production is the bottleneck, not the mats.
Can you supply against a specific DIN or EN clause?
Yes. Send the clause number and we reply with the matching drawing and available test data, so your architect can check it before the tender closes.
Do you handle installation?
Remote supervision is standard. For packages above roughly 40 pallets we can send a technician for commissioning.
Planning a sports hall fit-out for the next school year? Send us your floor plan and equipment schedule, and we will return a layout drawing and a costed package within five working days.