When a school authority in North Rhine-Westphalia reopened its refurbished two-court sports hall last autumn, the brief looked simple: replace everything from the basketball backstops to the mat trolleys. In practice it meant matching DIN 18032-3 impact requirements, RAL-matched powder coating, and a 22-week window that left no room for a second production run.

This is how the package was specified, built and shipped — and what we would quote differently next time.

Two-court school sports hall in Germany equipped with wall-mounted basketball backstops and volleyball posts

The programme at a glance

LocalizaçãoNorth Rhine-Westphalia, Alemanha
InstalaçãoTwo-court school sports hall, 1,150 m² playing area
Scope6 wall-mounted backstops, 4 volleyball post sets, 90 gymnastics mats, 8 table tennis tables, 24 trolleys
Standards referencedDIN 18032-3 (ball impact), EN 1270, EN 913, EN 14468-1
Produção liderar tempo26 days from approved drawings
Remessa1 × 40HQ to Hamburg + 3 air-freight pallets for the opening event
On siteRemote installation supervision, printed 1:50 layout drawings

Why German school halls are specified differently

Three requirements shaped almost every decision on this project, and they are the same three that come up in most German tenders we see.

Ball-impact segurança vem first

Under DIN 18032-3, a hall has to absorb a ball thrown at match speed without the wall fittings becoming a hazard. That is why wall-mounted backstops here are specified with folding arms that sit flat against the wall when not in use, and why every anchoring plate is calculated rather than picked from a catalogue.

Empty two-court sports hall with wooden flooring before equipment installation

Mats have to survive daily stacking

A 40 mm mat that loses its shape after one term is a false economy. We quoted 30 kg/m³ foam with a reinforced PVC cover and hook-and-loop edges, because the hall stores all 90 mats upright in trolleys twice a day.

Um Fornecedor, um desenho definir

The authority did not want to coordinate a backstop vendor, a mat vendor and a table tennis vendor across three delivery windows. Consolidating the package into one container and one set of layout drawings was worth more to them than the last two percent of unit price.

The equipment package, item by item

ItemEspecificaçãoQty
Wall-mounted basketball backstop1800 × 1050 mm acrylic board, 3.05 m rim height, folding arms, powder-coated frame6
Volleyball publicar definir4-post system, net height adjustable 2.24–2.43 m, padded bases4
Gymnastics mat2000 × 1000 × 40 mm, 30 kg/m³ foam, anti-slip PVC cover90
Mesa tennis mesa25 mm top, EN 14468-1, folding, four braked wheels8
Ball and mat trolley150 kg load, 1.5 m depth to fit existing cupboards24

How the order actually ran

Three details that took the longest

1. The wall, not the hoop. The playing-end wall was masonry, the side walls were stud partitions. One anchor schedule would have been wrong on half the hall. We asked for close-up photos of each wall and supplied two plate variants — a small change that avoided drill failures on site.

2. Mat armazenar depth. The hall's existing cupboards were 1.8 m deep, but the doors only opened to 1.5 m. Standard trolleys would have jammed. We shortened the frame rather than asking the school to rebuild furniture that had just been installed.

3. RAL 5015 versus RAL 5017. Two blues that look identical on a monitor and obviously different on a 1,150 m² floor. Physical chips settled it in a day. For any colour-critical project, insist on a physical sample before production.

Packing and paperwork for EU buyers

Mats travelled rolled in woven bags with edge protection; frames were crated with corner blocks and steel strapping. All timber was ISPM-15 heat-treated and stamped. For the German consignee we supplied HS codes, packing lists by pallet, and material and test reports for the standards named in the tender on request. Nothing in the shipment needed re-packing at the port — which is the outcome that matters when a school opening date is fixed.

Perguntas frequentes

What lead time should a German school plan for?
Eight to ten weeks door to door for a complete hall package, assuming drawings are approved before the summer break. Backstop production is the bottleneck, not the mats.

Can you supply against a specific DIN or EN clause?
Yes. Send the clause number and we reply with the matching drawing and available test data, so your architect can check it before the tender closes.

Do you handle installation?
Remote supervision is standard. For packages above roughly 40 pallets we can send a technician for commissioning.

Planning a sports hall fit-out for the next school year? Send us your floor plan and equipment schedule, and we will return a layout drawing and a costed package within five working days.

Produtos relacionados

Nossos produtos mais vendidos de Artigos esportivos com qualidade premium e preços competitivos

Ver todos os produtos
Número de contato:+86 13230761319
WeChat QR code
WhatsApp QR code Conversar agora
Voltar ao topo